The Grit Extractor screw is always provided as a separate piece. It just needs to be positioned into the tank. This can take 1 hour if the installation is simple. Schedule 2 hours.
3. Wiring
Wiring can be a fast activity if the panel is mounted close and flexible conduit is used. If cable raceways are more complicated, it can take longer.
Normally all wiring is 2 hours if all the raceways and conduits are laid ahead of time.
- The Blower is physically mounted to the Seditank Main Tank, so only wiring back to main panel is required|
Wire Grit Extractor screw
Wire Horizontal Grit Screw
4. Bring in Mains Power to Seditank Control panel
This is all in function of how the wiring to the building is done. This can take 15 minutes if the connection is already near the panel.