Scrudrain O&M Schedule

Scrudrain O&M Schedule


Frequency
O&M TASK DESCRIPTION
TIME TO COMPLETE
Every Working Day
Verify that the washing system operates properly
2 min.
Every 500 hours
Grease Bearing
1 min.
Every 5 years
Replace Bearing
2 hours
Replace Belt
Every 5-7 years
1 day



    • Related Articles

    • How to schedule maintenance on my centrifuge

      Maintenance Component Maintenance Task Interval Duration Transmission belt Check belt tension Every 800-1000 working hours 30min. Replace belt Every 10000 working hours 2 hours Bearing Grease Every 100 working hours 15min. Check integrity Every 2500 ...
    • How to Run the Draimad

      There are two videos that show the operational aspects of the Draimad DRAIMAD: RUNNING THE DRAIMAD DRAIMAD: O&M TRAINING 
    • How to resolve Oil Cooling Alarm

      If you cannot reset the alarm after letting the machine rest and reset, then you can perform these troubleshooting steps. Check physical condition If you have an oil cooling alarm you must verify and ensure that there is no physical reason; such as ...
    • How to go from 3 to 2 phase with the Decanter Centrifuge with the kit?

      If your Decanter Centrifuge was ordered with a special kit, it can be changed from 2 to 3 phases and vice versa From 3 to 2 phases 1.         Replace the oil levels with the plugs; ensure that there are O-rings on the plugs 2.Remove weir plates ...
    • How to adjust shutdown run time or conveyor run time on CBB HMI

      This is password protected and the password changes randomly everyday and must be generated by us. Contact DRYCAKE support for further assistance. How to Enter PASSWORD: 1. With decanter stopped, go to page of the Password and Connection HMI reported ...